Which form is used for the initial cost estimate of a major project in the Military Construction, Army program?

Prepare effectively for the Prospect Budget Training 254 Test. Utilize flashcards and multiple choice questions, each with hints and detailed explanations. Ace your exam!

Multiple Choice

Which form is used for the initial cost estimate of a major project in the Military Construction, Army program?

Explanation:
For a major Army Military Construction project, the initial cost estimate is documented on DA Form 1391, Project Data. This form collects the essential details of the proposal—scope, location, estimated total cost, work phases, and a brief justification—and serves as the official starting point for programming and budgeting within the PPBE system. It provides the baseline figures used to evaluate options and secure funding. Other forms serve different purposes or later stages, so they aren’t used to capture the initial MilCon cost estimate.

For a major Army Military Construction project, the initial cost estimate is documented on DA Form 1391, Project Data. This form collects the essential details of the proposal—scope, location, estimated total cost, work phases, and a brief justification—and serves as the official starting point for programming and budgeting within the PPBE system. It provides the baseline figures used to evaluate options and secure funding. Other forms serve different purposes or later stages, so they aren’t used to capture the initial MilCon cost estimate.